Ventura Estates Plaza
Duration: June 2017 to June 2018 Location: Thousand Oaks, California Client: OnPoint Development England|Ecology completed a series of site visits, surveys, and reports documenting the extent of potential impacts to coastal sage scrub by a proposed shopping center due to the presence of nearby nesting California Gnatcatchers. England|Ecology assisted the client in developing appropriate mitigation…
-
Salyer Mutual Water Company Technical Assistance Work Plan 5013-A
Duration: May 2018 to December 2018 Location: Salyer, Trinity County, California Client: California Water Resources Control Board England|Ecology was retained by Northgate Environmental to analyze the effect on biological resources of a proposed water infrastructure project including wells, tanks, and distribution lines, in the rural community of Salyer. Fieldwork included mapping of vegetation communities and…
-
Anza Mutual Water Company Technical Assistance Work Plan 5022
Duration: January 2017 to December 2018 Location: Anza, Riverside County, California Client: California Water Resources Control Board England|Ecology was retained by Northgate Environmental to analyze the effect on biological resources of a proposed water infrastructure project including wells, tanks, and distribution lines, in the rural community of Anza. Fieldwork included mapping of vegetation communities and…
-
South Mesa Water Company
Duration: August 2021 to August 2022 Location: Calimesa, Riverside County, California Client: California Water Resources Control Board The project proposed improvements to above- and below-ground water infrastructure in two distinct areas located along the Riverside and San Bernardino County line along the southern border of the City of Yucaipa and northern border of the City…
-
Owyhee Roads Fuelbreak Project
Duration: July 2017 to October 2017 Location: Humboldt County, Nevada Client: US Bureau of Land Management England|Ecology was contracted by the US Bureau of Land Management (BLM) to conduct surveys for Pygmy Rabbit on 2,068 acres of BLM-managed lands as part of the Owhyee Roads Fuelbreak Project. Two subcontractors were trained on survey methodology and…
-
Southern California Edison On-Call Biological Support
Duration: January 2010 to March 2023 Location: Throughout Southern California Client: Southern California Edison Provided a wide range of on-call biological support throughout the Southern California Edison service area. Services provided included surveys for nesting birds, special status species, raptors, and other biological constraints. Roles on various contracts and work assignments included biological surveys, monitoring,…
-
Antelope Valley Solar – Phase 2
Duration: October 2018 to October 2022 Location: Kern County, California Client: Greenskies As project manager and Director of Biological Resources at Bargas Environmental Consulting, England was initially part of a team of biologists that supported biological monitoring required under the Mitigation Monitoring and Reporting Program and Conditional Use Permit No. 201300170 conditions of approval for…
-
Montebello Hills Conservation and Development Project
Duration: January 2007 to December 2009 Location: Montebello, Los Angeles County, California Client: Cook-Hill Properties As project manager and Director of Biological Services for Natural Resource Consultants, England managed a large team of biologists, attended regular client meetings to help develop a strategy for project development and impact mitigation, conducted fieldwork, conducted surveys and monitoring…
-
Terranea Resort
Duration: January 2005 to July 2008 Location: Rancho Palos Verdes, Los Angeles County, California Client: Long Point Development As project manager and Director of Biological Services for Natural Resource Consultants, England led a team in the conduct of dudleya and California Gnatcatcher surveys, vegetation mapping, and collaborated with the client and other consultants on the…
-
Tehachapi Renewable Transmission Project
Duration: January 2010 to October 2016 Location: Kern, Los Angeles, Riverside, and San Bernardino Counties, California Client: Southern California Edison During various times on this large scale utility project, duties included construction monitoring and field surveys, including one year as the full time biologist at the Vincent Substation expansion. I ended work on this project…